The jack-in pile method

A pile is gripped by the hydraulic jacking system and pressed into the ground by continuous force. The jack-in force is recorded as it goes, so each pile proves itself as it is installed.

Procedure

  1. 01

    Position

    The machine walks on its sleepers to the pile point.

  2. 02

    Place and grip

    A precast pile is placed and sequenced for piling, then gripped.

  3. 03

    Jack in

    The starter pile is jacked in hydraulically. There is no hammering.

  4. 04

    Weld

    The second pile is shafted through and welded to the first, at ground level under the main body.

  5. 05

    Press and record

    Jack-in force is recorded for every 0.3 m (1 ft) of penetration.

  6. 06

    Set

    A set is taken when the jack-in force picks up, showing the pile has reached a bearing stratum.

  7. 07

    Verify

    Normally the pile is jacked to sustain 2 times its working load, like a static load test carried out in an accelerated manner.

Parts of the machine

Main support frame
The frame the jacking cylinders react against.
Patented grip jacking system
Grips the pile and presses it into the ground.
Operating control panel
Where the operator controls jacking, gripping and walking.
Support sleepers
Long and short sleepers carry the machine and let it walk between pile points.
Lateral movement mechanism
Moves the machine in the X and Y directions and turns it.

Verification

Jack-in force is recorded for every 0.3 m of penetration, and a set is taken when the force picks up, showing the pile has reached a bearing stratum. Normally the pile is jacked to sustain 2 times its working load, which works like a static load test carried out in an accelerated manner. Because every pile is installed the same way, the capacity of every pile is verified.

In erratic limestone, the high jack-in force also ensures good contact between the pile tip and the bedrock.